Hi PIerre,
Gantt : what happened with the "task links" option ?
Noting happens here when I click on it.
Before, I could choose how the Gantt should manage the time between tasks, etc.
Thanks!
 

Comments

Works fine here...
Have you tried the Task links sub-menus ? 
There are now 3 modes
The actual Task links button simply toggles the display of the links. The behavior is determined by the sub-menu settings:
  1. None
  2. Use Task dependencies
  3. Locked relationships
HTH !
 
Pierre_Admin

Armando

2015/04/01 18:23

In reply to by Pierre_Admin

[quote=Pierre_Admin]
Works fine here...
Have you tried the Task links sub-menus ? 
There are now 3 modes
The actual Task links button simply toggles the display of the links. The behavior is determined by the sub-menu settings:
  1. None
  2. Use Task dependencies
  3. Locked relationships
HTH !
 
Pierre_Admin
[/quote]
 
Thanks. I had an old version of the button... That explains everything!! 
-------------------------------------------------------