Submitted by Jon on 2010/10/03 17:01 How do I delete or re-assign a dependency? Thanks Jon Comments One way is to delete the value in NextTaskID Log in or register to post comments Thank you Pierre. I thought there must be a way (are there others?), but could not find references in the online manual. Jon Log in or register to post comments Other than the visual benefit of the connection between two dependent tasks, is there any other functionality that is provided by making one task depended on a predecessor? Log in or register to post comments I guess you could make a filter to only show certain task Ids or next asks Ids ? That's how I used it a few times. Log in or register to post comments If you have ideas on how to improve it, don't hesitate to suggest. The first that comes to mind, is to highlight (color or other) the next task that can be done (those, not done, with all predecessors marked as done) Log in or register to post comments Log in or register to post comments
Thank you Pierre. I thought there must be a way (are there others?), but could not find references in the online manual. Jon Log in or register to post comments
Other than the visual benefit of the connection between two dependent tasks, is there any other functionality that is provided by making one task depended on a predecessor? Log in or register to post comments
I guess you could make a filter to only show certain task Ids or next asks Ids ? That's how I used it a few times. Log in or register to post comments
If you have ideas on how to improve it, don't hesitate to suggest. The first that comes to mind, is to highlight (color or other) the next task that can be done (those, not done, with all predecessors marked as done) Log in or register to post comments