Submitted by Jon on 2013/04/03 14:13
Using the latest 8A.
 
In a new, blank database, I have a gantt set up to track some projects. The gantt is blank. The overview is on. I click on month or year and the gantt displays the region in the vicinity of the current date. However, if I click on week, day or hour I am taken back more than a year to 2012.
 
Also, after doing as described above, if I click in the gantt or in the outline area IQ locks up and has to be terminated using TM. This does not happen every time, but frequently enough to prevent me from using this feature of IQ.

 
Can someone confirm?
 
Jon

Comments

A couple more issues:
 
I am using the hourly display. As described earlier, the gantt displays the incorrect current date in this mode (about 1 year earlier). I enter a task and fill in the start and end dates. To see the bar in the gantt, I have to click on the over view display because the date is one year too early. Now, if I drag the percent complete in the gantt bar, the corresponding column is not updated in the outline (I have the field displayed). It will only update after refreshing the grid. That is the first issue. The second is after refreshing, I am taken back to the original, incorrect date and have to navigate back. This does not happen if II use weekly, monthly or year. Only hour and day.
 
Jon