Submitted by Pierre_Admin on 2009/05/14 13:03
Originally posted by Janrif in Mantis:
[quote]
In graphic calendar, user enters appt
start date = (pick a date)
end date = (pick a later date)
all day event

graphic calendar display is correct
In grid all appts show up as start date
[/quote]
This is by design. Start date and item duration define the calendar item. If you want, you can define an End Date (=start date + item duration)
[quote]
This is one of those date issues that confuses me. It appears to me that ApptDate is what you call 'start date'. I have neither 'Start Date' nor 'End Date' in my field list.
So what's the difference between ApptDate & StartDate?
[/quote]
You can rename any fields, but it is field ID 50 that is used for appointments. See the field management dialog. Also, when you create an appointment, check the Filled Fields section of the properties pane. You should see at least 3 values:
- FieldID 1: Item: Appointment text
- FieldID 50: Appointments: Appointment date
- FieldID 51: ItemDuration: Appointment duration in hrs